Oracle sent a formal force majeure notice to a Blue Owl Capital unit over Project Jupiter, a step that could let it delay some payments if the New Mexico data center misses its 2028 opening, Bloomberg reports.
The 1,400-acre campus in southern New Mexico is part of the Stargate initiative involving Oracle, OpenAI and SoftBank. It is designed for about 2.45 gigawatts of computing capacity. Stack Infrastructure, a Blue Owl company, is developing the site, with Oracle as the main tenant.
Advertisement
An Energy Transfer gas pipeline meant to supply the site is nearly six months behind, with service now expected Feb. 1, 2027. The delay followed repeated permit denials by the State Land Office and a route change. An air-quality permit for the Bloom Energy fuel cells that would power the campus is still pending. Residents and environmental groups have also opposed the project over water use and air pollution.
Bloomberg reported the notice could allow Oracle to postpone rent under some conditions, depending on the contract terms. An Oracle spokesperson said, “Project Jupiter remains on our planned schedule,” and the company called such notices common on projects of this size, Bloomberg reported. A Blue Owl spokesman said the notice does not change the financial commitments. Oracle shares fell after the news.
About This Story
Daily Reports is Brant.One’s news roundup. Each day we gather the New Mexico stories worth knowing from newsrooms across the state, sum them up and point you to the source. This one comes from Bloomberg’s reporting, and their original story has the interviews and full details.
Editor’s note: Updated Oct. 31, 2026. This story is now part of Daily Reports, our New Mexico news roundup, and was revised to credit Bloomberg’s original reporting. Learn how Daily Reports works in our editorial standards.